Construction Schedule

Station construction will begin in April 2013 and finish in July 2014. Depending on the station, construction will take 12-14 weeks. For approximately the first 8 weeks of that time, about 100 feet of the traffic lane closest to the station will be blocked. For approximately the last 4 weeks of construction, the road will be open and the only construction activity will be on the sidewalk and right-of-way off the road.

There are many other construction projects taking place during the BRT station construction (City of Grand Rapids, Michigan Department of Transportation, etc.). Unless specifically noted, The Rapid and Christman Construction are only involved/supervising construction at the specific station locations noted. The scope of construction at each station only covers the station's "footprint" and approximately 100 feet of roadway immediately in front of each station.

This schedule is subject to change, and all construction plans have been made with the intention of having as minimal of an impact on businesses, properties, and community events as possible.

For a downloadable PDF of the construction schedule, please click here. (199 KB, PDF)

Division Avenue Bus Rapid Transit (BRT) Project Construction Schedule

STATIONLOCATIONSTATION WORK DATES
STATIONTYPELOCATIONSHELTERSCHRISTMAN SITE WORKSTATION STRUCTURE UP
STA 09 IB Fulton/Ransom48' A - LEVELGrand Rapids1IB/NB4/1/2013 - 7/25/20138/30/2013
STA 23 Division/Southview48' A - LEVELGrand Rapids1IB/DT4/1/2013 - 5/28/20137/31/2013
STA 33 IB Division/60th48' B - LEVELKentwood1IB/SB4/1/2013 - 6/7/20139/11/2013
STA 21 IB Division/Burton48' B - LEVELGrand Rapids1IB/DT4/8/2013 - 7/25/20136/17/2013
STA 07 IB Ransom/Crescent32' A - LEVELGrand Rapids1IB/NB4/9/2013 - 6/19/20138/19/2013
STA 08 OB Ransom/Crescent32' A - LEVELGrand Rapids1OB/NB4/9/2013 - 6/20/20138/26/2013
STA 31 IB Division/54th48' B - LEVELKentwood1IB/SB4/10/2013 - 7/23/20136/24/2013
STA 19 IB Division/Cottage Grove48' A - LEVELGrand Rapids1IB/DT4/22/2013 - 7/25/20137/1/2013
STA 29 IB Division/44th48' A - LEVELKentwood1IB/SB4/25/2013 - 7/19/20137/10/2013
STA 12 OB Jefferson/St. Mary's48' A - LEVELGrand Rapids1OB/NB4/29/2013 - 7/23/20137/8/2013
STA 17 IB Division/Green48' A - LEVELGrand Rapids1IB/DT4/29/2013 - 7/25/20137/17/2013
STA 27 IB Division/36th48' A - LEVELWyoming1IB/SB5/10/2013 - 8/2/20137/24/2013
STA 04 IB Monroe/Devos Place32' A - LEVELGrand Rapids1IB/NB5/13/2013 - 7/3/201310/17/2013
STA 02 IB Monroe/Louis32' A - LEVELGrand Rapids1IB/NB5/15/2013 - 7/3/201310/9/2013
STA 25 IB Division/28th48' A - LEVELGrand Rapids1IB/SB6/6/2013 - 8/26/20138/12/2013
STA 15 IB Division/Franklin32' B - LEVELGrand Rapids1IB/DT6/19/2013 - 8/23/20139/13/2013
STA 01 OB Monroe/Louis32' A - LEVELGrand Rapids1OB/NB7/8/2013 - 8/30/201310/7/2013
STA 03 OB Monroe/Devos Place48' A - LEVELGrand Rapids1OB/NB7/10/2013 - 9/9/20139/27/2013
STA 06 IB Michigan/Bostwick48' A - STEPPEDGrand Rapids1IB/NB7/15/2013 - 9/2/20136/6/2014
STA 10 OB Ransom/Fulton48' B - LEVELGrand Rapids1OB/NB7/22/2013 - 9/25/201310/16/2013
STA 18 OB Division/Hall48' B - LEVELGrand Rapids1OB/DT7/29/2013 - 9/20/201310/11/2013
STA 30 OB Division/44th48' A - LEVELWyoming1OB/SB7/29/2013 - 9/20/201310/30/2013
STA 20 OB Division/Cottage Grove48' A - LEVELGrand Rapids1OB/DT8/5/2013 - 10/1/201310/23/2013
STA 24 OB Division/Southview48' A - LEVELWyoming1OB/DT9/3/2013 - 10/25/201311/18/2013
STA 28 OB Division/36th48' A - LEVELWyoming1OB/SB8/15/2013 - 11/18/201310/25/2013
STA 22 OB Division/Burton48' A - LEVELGrand Rapids1OB/DT8/19/2013 - 10/29/201311/4/2013
STA 16 OB Division/Franklin48' A - LEVELGrand Rapids1OB/DT8/26/2013 - 10/31/201310/2/2013
STA 32 OB Division/54th48' A - LEVELWyoming1OB/SB9/5/2013 - 11/4/201311/25/2013
STA 26 OB Division/28th 48' B - LEVELWyoming1OB/SB9/12/2013 - 11/19/201311/14/2013
STA 13 IB Division/McConnell48' A - LEVELGrand Rapids1IB/NB3/19/2014 - 5/16/20146/9/2014
STA 05 OB Michigan/Bostwick48' A - STEPPEDGrand Rapids1OB/NB4/7/2014 - 5/23/20145/21/2014
STA 11 IB Jefferson/St. Mary's48' A - LEVELGrand Rapids1IB/NB4/14/2014 - 6/11/20146/1/2014
STA 14 OB Division/McConnell48' A - LEVELGrand Rapids1OB/NB4/16/2014 - 7/1/20146/1/2014
STA 34 Central Station48' A - LEVELGrand Rapids13/31/2014 - 5/21/20145/21/2014